Power Grid Enhancement Project

Brief Summary
The main objective of the project is to satisfy the increasing demand for electricity through expanding the capacity of power transmission infrastructure in Java-Bali, Sumatra, Kalimantan and Sulawesi. Upon completion, the project will enable reliable and efficient electricity supply of an additional 10,135 MVA. The project will contribute to the government’s overall goal of strengthening the power transmission grid capacity to supply 332 TWh (by 2020) from 228 TWh (in 2015) and increasing the electrification rate in the country to 97% from the current 84.3%.
Location
Country
Sector
Energy
Project Status
Active
Start date
9 January 2017
End date
11 September 2019